Traditional procurement method
Contents |
[edit] What is the traditional procurement route?
The traditional procurement route involves separating design from construction. The client first appoints consultants to design the project in detail (and often to ensure cost control and inspect the construction works as they proceed), and a contractor is then appointed for the construction of the project on a single-stage competitive basis.The contractor’s responsibilities include workmanship, materials and work undertaken by suppliers and subcontractors. They are not responsible for the design (other than temporary works), although some traditional contracts may allow the contractor to design specific parts of the works.
Traditional procurement is typically undertaken under a lump sum contract. A single ‘lump sum’ price for all the works is agreed before the works begin, then stage payments are made as the works proceed. This is appropriate where the project is well defined when tenders are sought, and significant changes to requirements are unlikely. This allows the contractor to accurately price the works they are being asked to carry out.
[edit] How popular is the traditional procurement route?
Traditional procurement remains the most commonly-used method of procuring building works.
The National Construction Contracts and Law Report 2018, published by NBS, suggested the following mix of procurement routes in the construction industry:
- Traditional procurement 46%
- Design and build 41%
- Partnering / alliancing 3%
- Construction management 3%
- Contractor approved without any tender process 2%
- Measured term 1%
- PFI / PPP 1%
- Cost plus 1%
- Management contracting 1%
For more information see: What is the most common procurement route?
[edit] When is the traditional procurement route appropriate?
The traditional procurement route is generally suitable where the client wishes to retain control over decisions relating to the design and quality of the project. However, a full package of detailed information is required before a contractor can be appointed, and this can make it slower and more expensive than some other forms of procurement. It also means that the contractor is not involved in the design decisions, and so it can result in issues with buildability.
[edit] What are the key characteristics of the traditional procurement route?
Key characteristics of traditional procurement include:
- Consultants retaining control over design and quality. This may result in a higher standard of project than some other procurement routes.
- Consultants are responsible for valuations and agreeing payments.
- The contractor generally has no design duties, but where this is necessary for some aspect of a project, the contract should include clear wording to this effect.
- There must be adequate time before tenders are invited to allow for the production of a complete set of drawings and other documents. This means the traditional procurement route may be slower than some other routes.
- Contractors may submit claims if they do not receive the timely instructions and information, or if changes are made.
- The traditional method – or adaptations of it – can be used with approximate quantities, provisional sums or cost reimbursements where the nature or quantity of work cannot be accurately defined.
For further information see Traditional contract for construction.
For other methods see: Procurement routes.
[edit] Related articles on Designing Buildings
- Appointing consultants.
- Bill of quantities.
- Construction contract.
- Contract conditions.
- Contractor.
- Notifications during construction works
- Procurement route.
- Temporary works.
- Tender.
- Tender documentation.
- Traditional contract for construction
- Traditional contract: outline work plan.
- Traditional contract - pros and cons.
- Two-stage tender.
- Variations.
Featured articles and news
A case study and a warning to would-be developers
Creating four dwellings... after half a century of doing this job, why, oh why, is it so difficult?
Reform of the fire engineering profession
Fire Engineers Advisory Panel: Authoritative Statement, reactions and next steps.
Restoration and renewal of the Palace of Westminster
A complex project of cultural significance from full decant to EMI, opportunities and a potential a way forward.
Apprenticeships and the responsibility we share
Perspectives from the CIOB President as National Apprentice Week comes to a close.
The first line of defence against rain, wind and snow.
Building Safety recap January, 2026
What we missed at the end of last year, and at the start of this...
National Apprenticeship Week 2026, 9-15 Feb
Shining a light on the positive impacts for businesses, their apprentices and the wider economy alike.
Applications and benefits of acoustic flooring
From commercial to retail.
From solid to sprung and ribbed to raised.
Strengthening industry collaboration in Hong Kong
Hong Kong Institute of Construction and The Chartered Institute of Building sign Memorandum of Understanding.
A detailed description from the experts at Cornish Lime.
IHBC planning for growth with corporate plan development
Grow with the Institute by volunteering and CP25 consultation.
Connecting ambition and action for designers and specifiers.
Electrical skills gap deepens as apprenticeship starts fall despite surging demand says ECA.
Built environment bodies deepen joint action on EDI
B.E.Inclusive initiative agree next phase of joint equity, diversity and inclusion (EDI) action plan.
Recognising culture as key to sustainable economic growth
Creative UK Provocation paper: Culture as Growth Infrastructure.
























Comments
[edit] To make a comment about this article, or to suggest changes, click 'Add a comment' above. Separate your comments from any existing comments by inserting a horizontal line.